February 5, 2005: Bridging the Channel Gap
This week, the stay pipes and cables attached to the last pair of
anchors (316) were erected
The next morning, Feb 6, 2005: The concrete floor panals have been
placed and now the east deck is lower than the west deck.
From the old bridge where you can see my weekly photo spot - about
1 km next to the vertical loading machines
February 1, 2005: Starting the stay cable assembly
February 4, 2005: Finished stay cable assembly